Dec 09,2021

Project Update: Baxter Road Hotel

Highlights for the month include the completion of the Mock-Up Room (including inspection and sign-off by Marriot) Roberts Co

After 3 months down on site, there’s been great progress made by the project team. Highlights for the month include the completion of the Mock-Up Room (including inspection and sign-off by Marriot), establishment of jump form, completing first pour to Ground Floor slab and completion of vertical cores to Ground Floor.

The team are continuing to navigate the unique site constraints and limited working space, which will become slightly easier once the remainder of ground floor slab is poured. Early December will see Ground Floor to Level 2 (double height) precast panels installed, and forming of the Level 1 suspended slab underway.