Oct 28,2022

Melbourne Project Update: 500 Bourke Street

Project Udate: 500 Bourke Street

500 Bourke Street Update

  • Demolition – office tower strip out & ground plane structural demolition are rapidly approaching completion and thereafter demobilisation of demo contractor – always a positive milestone.
  • Facade rectification work progressing well
  • Good safety compliance as captured on both internal & external audits
  • New starter Alex Favaloro – welcome aboard! Alex has settled in quickly and is having a positive impact to the team
  • Hazmat removal approaching completion – high level of stakeholder interactions required
  • Services rough-in to tower floors progressing well – finishes to follow
  • Management of existing floor deflections and existing screed remains intensive
  • Resolution reached on a number of Latent Conditions and client issues, including FRV Approvals and Underpinning to B1
  • Management of live retail tenancies ongoing and to the satisfaction of all stakeholders
  • New site office on Level 1 approaching completion.